This example shows how to create a Preventative Maintenance plan for Pavement so when a pavement segment’s Estimated OCI reaches 85 a crack seal is done and to schedule a task to Grind when the minimum condition is reached.

  1. Click Screen Shot 2018-04-12 at 3.27.44 PM.png>Preventative Maintenance.
  2. Select Pavement.
  3. Click Create Plan.
  4. Enter the plan name, Urban Arterial Maintenance.
  5. Click Edit Filter.
  6. Create a filter where the Functional Classification is Urban Arterial and click Apply.
  7. Click Add Activity and select Seal.
  8. Click Add Trigger and select Conditional.
  9. Define the trigger with the following values:
  • "Estimated OCI
  • Falls below 85
  1. Click the Save Trigger icon.
  2. Click Add Activity and select Grind.
  3. Click Add Trigger and select Condition.
  4. Select Minimum is Reached.
  5. Click the Save Trigger icon.
  6. Click Activate Plan.