Create a Custom Resource Estimate

You must have administrator rights to access this feature.

  1. Click iAdministration_sm.png>Resource Estimates Manager.
  2. Select an Asset Type.
  3. Select an Activity.
  4. Click Create.
  5. In the Labor Estimates section, select a Method.
  • Use Cartegraph Calculated Estimates: Resource estimates are calculated using the data available in the system.
  • Set Custom Estimates: Set the hours and cost values for Labor Estimates and cost for Equipment Estimates, Material Estimates, and Other Estimates.
  • Set Custom Estimates With a Quantity: Set the hours and cost values per unit for Labor Estimates and cost per unit for Equipment Estimates, Material Estimates, and Other Estimates.
  1. In the Equipment Estimates section, select a Method.
  2. In the Materials Estimates section, select a Method.
  3. In the Other Estimates section, select a Method.
  4. Click Save.

The next time a task with this asset/activity combination is created, the estimates are calculated using these settings.