In this example, a protocol is created that includes all local roadways. The protocol recommends the following activities:

  • Overlay if the road's Estimated OCI falls between 21 and 45. Once performed, this activity should skip 2 years before being performed again and funds come from the Major Activities budget.
  • Patch every 3 years from the Minor Activities budget.
  • Crack Seal for asphalt roads once for the Scenario from the Minor Activities budget.

These activity recommendations are defined as triggers under the local roadways protocol.

Create a Protocol

  1. Click 2018-04-17_0919.png>Library Manager.
  2. Go to the Protocols Library.
  3. Click Create.
  4. Name protocol Local Roadways.
  5. Select Pavement from the Asset Type field.
  6. Click Filter.
  7. Select Functional Classification.
  8. Select Is as the operator.
  9. Select Local from the Functional Classification Type field.
  10. Click Apply.
  11. Click Finish.

Now it's time to add the Triggers.

Create Triggers

  1. In the Protocol List view, select Local Roadways and click View.
  2. In the Triggers section, click Add.
  3. Select Overlay from the Activity field.
  4. In the Cost field enter the dollar amount of (50000.00).
  5. Select Major Activities from the Budget Category field.
  6. Enter Estimated OCI From with 21.
  7. Enter Estimated OCI Through with 45.
  8. In the Plan Years to Skip Before Eligible Again field, enter 2.
  9. Click Save.

Set the Trigger Activity

  1. Select Patch from the Activity field.
  2. In the Cost field enter the calculation of ([Length.Amount] * 0.70).
  3. Select Minor Activities from the Budget Category field.
  4. In the Plan Years to Skip Before Eligible Again field, enter 2.
  5. Click Save.
  6. Select Crack Seal from the Activity field.
  7. In the Cost field, enter the calculation ([Length.Amount] * 0.40).
  8. Select Minor Activities from the Budget Category field.
  9. Click Filter under the Filter Text field to create the filter.
  10. Select Pavement Classification.
  11. Select Is as the operator.
  12. Select Asphalt from the Pavement Classification field.
  13. Click Apply.
  14. In the Plan Years to Skip Before Eligible Again field, enter 99.