Add Existing Task to Existing Work Order

This feature may not be available in every package. Not sure if you have this feature or you want to learn more about it? Send us a message at support@cartegraph.com.

 

List View

  1. Click the Work>Task tabs.

Add a Task Layer.

  1. Select one or more Tasks on the List view.

The Task dates must fall into the Work Order’s date range.

  1. Click Actions>Add to Existing Work Order.
  2. Select the Work Order ID.
  3. Click Add.

The selected tasks are associated to the selected Work Order.

Detail View

  1. Click the Work>Task tabs.

Add a Task Layer.

  1. Navigate to the desired Task and click View.

The Task dates must fall into the Work Order’s date range.

  1. Click Actions>Add to Existing Work Order.
  2. Select the Work Order ID.
  3. Click Add.

The selected tasks are associated to the selected Work Order.

 