Skip to main content
Cartegraph Campus

Add Existing Task to Existing Work Order

You must have a Cartegraph OMS advanced feature extension to access this feature.

 

List View

  1. Click the Work>Task tabs.

Add a Task Layer.

  1. Select one or more Tasks on the List view.

The Task dates must fall into the Work Order’s date range.

  1. Click Actions>Add to Existing Work Order.
  2. Select the Work Order ID.
  3. Click Add.

The selected tasks are associated to the selected Work Order.

Detail View

  1. Click the Work>Task tabs.

Add a Task Layer.

  1. Navigate to the desired Task and click View.

The Task dates must fall into the Work Order’s date range.

  1. Click Actions>Add to Existing Work Order.
  2. Select the Work Order ID.
  3. Click Add.

The selected tasks are associated to the selected Work Order.

 

  • Was this article helpful?